New access road, parking, wet & dry infrastructure and two (2) new turf soccer fields.

DJI_0611.jpeg
Image 12-14-23 at 6.31 PM.jpeg
Image 12-14-23 at 6.32 PM.jpeg
Image 12-14-23 at 6.32 PM (1).jpeg

December Progress

Transparent logo_edited.png

More Details:

  • Completed Installation of patch back asphalt at the existing parking lot.

  • Completed installation of 8-inch perforated storm drain lines under the two new artificial turf fields.

  • Continued establishing sub grade for concrete curb and gutter. 

  • Continued with construction and installation of concrete curb and gutter.

  • Mobilized their concrete curb machine for installation of concrete curb.

  • Started installation of 2-inch irrigation lines around the two new artificial turf fields.

  • Performed survey stakeout of concrete curb and gutter.

  • Continued with construction and installation of concrete curb and gutter.

  • Installed concrete overflow structures at bioswale basins. 

  • Received fence and post materials. 

  • Installed best management practices to mitigate storm water erosion.